Quantcast
Channel: José Santamarta Flórez
Viewing all 10409 articles
Browse latest View live

Supply of the first Gamesa G114-2.0 MW wind turbines in Europe

$
0
0
Gamesa, a global technology leader in wind energy, has reached an agreement with Eolus Vind, one of Sweden’s leading wind farm developers, for the supply of four of its G114-2.0 MW turbines in this Scandinavian market.

Under the terms of the agreement, Gamesa will supply, install and commission these 8 MW at the Nötåsen wind farm located in municipality of Sundsvall, starting this summer. The company will also provide the facility’s operation and maintenance (O&M) services for a period of five years.
This contract represents a milestone in Gamesa’s sales strategy as it marks the European debut of its new G114-2.0 MW turbine, designed to yield more power at lower cost at medium and low wind speed sites. This turbine delivers a higher capacity factor and reduces the cost of energy by as much as 10%. With this new order, Gamesa now has contracts and frameworks agreements for its G114-2.0 MW turbine covering 504 MW.
This is the second supply agreement between Gamesa and Eolus Vind for whom it already installed two 850 kW turbines. Also in Sweden, Gamesa recently supplied 20 MW to UK infrastructure manager John Laing at the Svartsvallberget farm which is currently in the process of being started up.
Blade de-icing system
As part of this project, Gamesa will install a system for detecting and eliminating ice on blades that has been custom-developed for Gamesa’s suite of 2.0-2.5 MW turbines. Gamesa’s portfolio of turbines includes products specifically configured and adapted for sites that undergo extreme weather conditions, including sub-zero temperatures. Against this backdrop, the company is also developing another ice prevention system in collaboration with VTT for its platform of 5.0 MW turbines.
Gamesa G114-2.0 MW
The Gamesa G114-2.0 MW wind turbine is a standard-bearer in the sector thanks to its low power density. This new product contributes to one of the company’s top priorities: significantly cutting the cost of energy of the products designed by Gamesa for medium and moderate wind speed sites.
With a rotor spanning 114 metres, the new turbine’s swept area is 38% greater than that of the G97-2.0 MW, while it produces up to 20% more energy a year. The G114-2.0 MW wind turbine, designed to maximise the performance of turbines installed in medium and moderate windy sites, is part of the company’s 2.0-2.5 MW platform, whose track record encompasses the installation of more than 15 GW worldwide and an availability record of over 98%.


Termosolar y energías renovables: Primera central de energía solar termoeléctrica de Kuwait

$
0
0
La presentación de ofertas para la primera fase del proyecto termosolar, que abarcará varias tecnologías, concluyó el 27 de noviembre de 2013.

Ya se conocen los seis consorcios preseleccionados para desarrollar la planta termosolar de 50 MW que formará parte del complejo kuwaití de energías renovables Shagaya y cinco de ellos están liderados por empresas españolas.
El pasado mes de junio, el Instituto de Kuwait para Investigación Científica (KISR, por sus siglas en inglés) presentó el proceso de licitación para la ingeniería, adquisición y construcción de la primera fase del parque de renovables Shagaya, de 70 MW, y comenzó a aceptar propuestas para los grupos de cualificación previa.
Está previsto que el proyecto, que abarca plantas de 50 MW termosolares (CSP, por sus siglas en inglés), 10 MW de solar fotovoltaica y 10 MW de eólica, suministre hasta 225.000 MWh a la red al año una vez que se complete, en la primera mitad de 2016. Para la primera planta, el Kuwait Institute for Scientific Research (KISR) optó por la tecnología cilindroparabólica, con 10 horas de almacenamiento en sales fundidas y un sistema de enfriamiento en seco para minimizar el consumo de agua.
La oferta más económica es de TSK
De los ocho consorcios de CSP cualificados, se han preseleccionado ahora seis para desarrollar la planta Shagaya, de 50 MW. De ellos, cinco están liderados por contratistas españoles. Esto no es algo sorprendente si se tiene en cuenta el largo liderazgo de España en el mercado global de la termolar.
La empresa de ingeniería TSK Electrónica y Electricidad y Kharafi National, con sede en Kuwait, presentaron la oferta más baja. De todas maneras, este criterio solo será un factor secundario, según indicó a CSP Today una persona que está involucrada en el sector. “El primer criterio será el cumplimiento técnico. Una vez que este se compruebe, el factor determinante será el precio del contrato”.
TSK se expandió a Oriente Medio en 2010, con proyectos en Arabia Saudí, la India y Bangladesh. La empresa cuenta con un largo historial en el sector termosolar y, actualmente, participa en la construcción de los proyectos independientes de energía Bokpoort, de 50 MW, en Sudáfrica, y Ouarzazate, de 160 MW, en Marruecos.
Como muchos desarrolladores de CSP españoles que han expandido enormemente sus negocios en el extranjero, el 95 % del trabajo de TSK en 2013 se realizó fuera de España. Con el fin de reforzar más su liderazgo tecnológico en el sector termosolar, el pasado mes de noviembre, TSK anunció la adquisición del fabricante de CSP alemán Flagsol. Esta firma se encargó del desarrollo de la tecnología de instalación solar cilindroparabólica para la planta de ciclo combinado solar integrado Kuraymat, en Egipto, y para Andasol, en España.
“Con esta operación, TSK se sitúa en una posición envidiable para competir en los ambiciosos planes de energía solar que han anunciado países como Arabia Saudí, Kuwait, Marruecos, Omán, Qatar o EAU y otros que también se están comprometiendo firmemente con la energía solar”, afirmó la empresa.
En Kuwait, TSK trabajaría con Kharafi National, un desarrollador de proyectos que ha dado varios pasos para participar en el mercado solar. En 2011, estableció Kharafi National Ralos, una sociedad conjunta con la empresa alemana Ralos New Energy. También firmó un memorando de acuerdo con la estadounidense GlassPoint que le permitía participar en los futuros proyectos de anegación por vapor del país. Un ejemplo es el de CSP que ha planificado Kuwait Oil Company (KOC) para la recuperación mejorada de petróleo.
Abener y Teyma contra Elecnor
Las filiales de Abengoa Abener y Teyma presentaron otra de las ofertas para la planta de CSP Shagaya. Se trata de dos empresas pioneras internacionales que han trabajado en varios proyectos a gran escala, como Shams 1, de 100 MW, en Abu Dhabi. La cartera de Abengoa abarca proyectos impactantes, desde cinco complejos solares en España hasta Solana (Arizona, EEUU), la planta cilindroparabólica más grande del mundo con 280 MWe y seis horas de capacidad de almacenamiento de energía térmica.
Actualmente, Abengoa está construyendo el proyecto Mojave Solar, una planta de CSP de 280 MW que se pondrá en marcha en 2014, así como dos instalaciones en Sudáfrica. Bader Al-Mulla & Brothers Co., uno de los grupos de ingeniería más grandes de la región del Golfo, trabajaría con las filiales de Abengoa en Kuwait. Puede aprovechar su experiencia en contratación electromecánica, petróleo y gas, acero estructural, conductos e instrumentación en la construcción de la planta de CSP Shagaya.
Elecnor presentó la tercera oferta. La firma, que ha construido plantas termosolares de 50 MW en España y logró 700 millones de euros de financiación para su desarrollo, formará equipo con Al Ghanim International General Trading & Contracting Co., un contratista de EPC de Kuwait que trabaja, sobre todo, en proyectos energéticos y cuenta con una cartera que representa, aproximadamente, al 30 % de la capacidad instalada de Kuwait.
“Elecnor posee la capacidad técnica y financiera necesaria para abordar el diseño, el suministro, la construcción, la puesta en marcha, la explotación y el mantenimiento de plantas de energía solar termoeléctrica que se basan en tecnología de colectores cilindroparabólicos”, declara la empresa.
Cobra y Abantia, también finalistas
Cobra Instalaciones y Servicios, que cuenta con una cartera de CSP que suma más de 500 MW, presentó la cuarta oferta. Solo en España, Cobra ofreció servicios de EPC para nueve plantas de CSP con tecnología parabólica de 50 MW, todas ellas con almacenamiento de vapor fundido. También es uno de los socios que financia la planta de CSP de torre central Crescent Dunes, de 110 MW (Nevada, EEUU).
Cobra realizó la oferta en colaboración con United Gulf Enterprises General Trading & Contracting Co. (Ugetco), una empresa de Kuwait que trabaja con sectores clave como el petróleo y el gas, la energía y el agua, y las infraestructuras. Según Ugetco, el grupo se centra en “ayudar a empresas internacionales a que lleven a cabo proyectos usando sus conocimientos y su experiencia en el mercado local”.
La empresa Abantia Instalaciones es la quinta española preseleccionada. Entre los proyectos que ha desarrollado figuran dos plantas de CSP en España, así como Borges, de 22,5 MW, que está  situada en la provincia de Lérida y es la primera instalación termosolar y de biomasa híbrida. La desarrolló con Comsa Emte en un tiempo récord de 20 meses. Con sedes en Qatar y Marruecos, Abantia ya está preparada para asumir proyectos en la región MENA.
El socio local de Abantia sería Burhan International Construction Co., miembro de Al-Wazan Trading, una de las mayores empresas de construcción de Kuwait. Burhan ejecuta proyectos relacionados con la infraestructura, el tratamiento de agua y las redes de distribución. Asimismo, ha ejecutado varios desarrollos para el Ministerio de Electricidad y Agua. Según el grupo, Burhan es una de las dos empresas clasificadas por el Gobierno de Kuwait como un “contratista de primer nivel para trabajos de construcción e infraestructuras”.
Por último, también ha sido preselccionada Larsen & Toubro Ltd (L&T), una de las empresas de construcción más grandes de la India.Las capacidades de L&T incluyen la fabricación de estructuras de seguimiento y fijas, así como la construcción de plantas.
La empresa india formó parte del consorcio liderado por IIT Mumbai que construyó la planta de CSP piloto de 1 MW para el Ministerio de Energías Nuevas y Renovables de la India. En Kuwait, L&T trabajaría con su empresa asociada L&T Kuwait Construction, una sociedad conjunta de L&T Ltd, de la India, y Bader Al Mulla & Brothers Company, de Kuwait.
¿Qué va a ser lo próximo?
Al ser un proyecto piloto, la construcción del parque de renovables Shagaya permitirá a Kuwait evaluar el rendimiento de diferentes tecnologías renovables de acuerdo con sus condiciones climáticas, realizar estudios de viabilidad económica y técnica y determinar cualquier deficiencia.
Aunque todavía no se ha anunciado la fecha oficial, se espera que se otorgue el contrato para el desarrollo de la planta durante este primer trimestre de 2014. El proyecto, financiado por el gobierno, es el primero de un plan dividido en tres fases propuesto por el KISR. Su objetivo final es llegar hasta los 2.000 MW para 2030, por lo que el potencial es enorme para todo el sector de la CSP.
http://www.evwind.com/wp-content/uploads/2013/03/ShamsCSP.jpg
En la conferencia Menasol, que se desarrollará el 6 y 7 de mayo en Dubhai, expertos del Instituto Fraunhofer para la Energía Solar y el Consejo Empresarial de Energía Limpia compartirán datos comerciales y tecnológicos sobre el mercado de la CSP en Kuwait.



 
 
 

Major Concentrated Solar Power (CSP) developers to discuss Southern Africa’s potential market

$
0
0

Namibia is preparing its first 50 MW concentrated solar power project and Botswana has too plans to include renewable energy amongst its energy portfolio.
Renewable energy projects are advancing rapidly in Southern Africa, with new government support for independent power producers (IPPs) and new interest from investors.

Southern Africa is seen by multiple analysts as one of the most important regions to develop renewable energies globally. Recently, 17 renewables projects were granted preferred bidder status under the last round of South Africa’s Renewable Energy Independent Power Producer Programme (REIPPP). Now, Namibia is preparing its first 50 MW concentrated solar power project and Botswana has too plans to include renewable energy amongst its energy portfolio.

Aaron Somolekae, Principal Engineer at the Department of Energy of Botswana told CSP Today that “the bankable feasibility study recommended 100MW as a PPP/IPP model, whereby Botswana Power Corporation will have a stake and an IPP/developer will have the majority stake. The amount of local private content will also play a small role. There may be potential for another 100MW as well” told In South Africa, an additional Window 3.5 takes place in March exclusively for CSP. 200 MW will be allocated and according to financing sources, there are 6 bidders so far involved in the round. During the last CSP Today “Securing Project Financing” webinar, developers voted in an industry poll that raising enough debt or equity commitments pre-bid submissions was the biggest financial challenge in the region.

Leading Spanish developer Abengoa with three CSP plants totalling 250 MW, Saudi ACWA Power and South African Emvelo with 50 and 100 MW trough plants respectively are meeting at CSP Today South Africa 2014 (8-9 April, Cape Town) to discuss the next steps for the CSP industry in the region with financial institutions such as Investec, DBSA or Standard Bank and government officials from South Africa, Botswana and Namibia.
 
 
 
 

More Than 250,000 Vehicle-to-Grid (V2G) Enabled Electric Vehicles Will be Sold From 2013 to 2022

$
0
0
Though negligible today, the market for plug-in electric vehicles (PEVs) equipped with vehicle-to-grid (V2G) technologies – which enable the vehicles to participate in ancillary services for the power grid – is expected to expand steadily in the coming years.  Compelling business models for V2G technologies are starting to emerge in select markets around the world, and it’s expected that individually owned electric vehicles will be able to participate in grid services in the second half of this decade.  

According to a recent report from Navigant Research, more than 250,000 V2G-enabled PEVs will be sold worldwide from 2013 to 2022.
“Plug-in electric vehicles can provide services to the grid by changing the rate at which they consume power, thereby reducing peak loads, or by providing power back to the grid, helping to balance loads on the grid,” says Scott Shepard, research analyst with Navigant Research.  “The benefits to operators also include smoothing the integration of renewable energy resources and generation revenue from ancillary services markets.”
The U.S. Department of Defense has been a significant proponent of V2G technology.  In early 2013, the Department announced that it would invest close to $20 million to install 500 V2G-enabled PEVs in military bases in specific U.S. electricity markets by the end of the year.  Additionally, demonstrations and pilot projects using fleet vehicles in the United States, various Western European countries, and Japan indicate that V2G technologies can serve as effective assets in various grid services, the report finds.
The report, “Vehicle to Grid Technologies”, analyzes the market opportunity for V2G technologies to be used to support grid reliability and stability.  The study considers various policy factors associated with the growth of V2G, as well as significant market drivers and barriers.  Global market forecasts for V2G-enabled PEVs and V2G capacity and revenue, segmented by region, extend through 2022.  The report also examines the major V2G technologies, provides case studies, and profiles key market participants.  An Executive Summary of the report is available for free download on the Navigant Research website.

   


Wind energy: Borusan EnBW signs framework agreement with Vestas for Turkish wind farm portfolio

$
0
0
German outfit EnBW Energie and Turkish player Borusan have signed a framework agreement with Vestas for wind turbines at five wind farms in Turkey totalling 207MW.

The Danish manufacturer will supply 67 of its V112 3MW wind turbines to be built in stages at five locations in Turkey. Each wind turbine will have a hub height of 84 meters and a rotor diameter of 112 metres.
The schemes are to be developed under the joint-venture Borusan EnBW Enerji and work on the first wind power project, a nine-turbine, 27MW extension to the Bandirma facility, will kick off shortly.
The Mersin project in the south of the country and the Bursa and Canakkale schemes in the north-west will each feature 16 turbines for 50MW capacities while the Izmir facility in the south-west will feature 10 turbines for a 30MW capacity.
“Our commitment in Turkey is an important building block of our corporate strategy and is based on our long-term strategic assessment of the Turkish energy market, which takes account of the generation capacities and technologies needed, above all in the expansion of renewable energies,” said EnBW chief executive Frank Mastiaux.
Borusan chief executive Agah Ugur added: “Borusan EnBW Enerji’s audacious step marks a milestone on the way to using the huge renewable energies potential of Turkey.”


 
 
 

Germany to expand offshore wind energy capacity fourfold in 2014

$
0
0
Germany will expand its offshore wind power capacity fourfold this year as projects totaling 1.5 gigawatts are expected to begin generating, according to Stiftung Offshore-Windenergie, an industry group.

Six wind farms including the 400-megawatt Global Tech I wind farm and EnBW Energie Baden-Wuerttemberg AG (EBK)’s 288-megawatt Baltic 2 wind farm are seen starting up in 2014, the group said today in a study commissioned by the Environment Ministry.
Two more wind farms are being built and expected to operate from next year, it said.
Three wind farms with a combined capacity of 520 megawatts are in operation in the German North and Baltic Sea. Construction of at least three more projects with 800 megawatts will start in the course of this and next year, it said.

 
 

Wind power: First wind farm in Mexico's Jalisco state

$
0
0
The wind farm in Jalisco has 28 wind turbines with a generating capacity of 1.8 MW each, giving the wind power plant a total generating capacity of 50.4 MW, or enough to meet the power needs of 72,000 households.
 
Officials have inaugurated the first wind farm in the western Mexican state of Jalisco, a wind power plant built with funds invested by the Dragon company and Grupo Salinas, the Energy Secretariat said.
The new wind farm is at an altitude of 2,500 meters (about 8,200 feet) above sea level, making it the highest facility of its kind in Latin America, Energy Secretary Pedro Joaquin Coldwell said.
Mexico needs to expand its electricity generation capacity by slightly more than 80 percent over the next 15 years and will have to build power plants with a capacity of about 55,000 MW to meet demand, Coldwell said.
The wind farm will keep more than 79,000 tons of CO2 from being emitted into the atmosphere.
The wind farm, which cost more than 1.4 billion pesos ($105 million), shows that efficiency and social responsibility can be combined, Grupo Salinas CEO Ricardo Salinas Pliego.
The green energy complex will boost Mexico's renewable energy capabilities, Federal Electricity Commission, or CFE, director Enrique Ochoa said.
Projects like the wind farm in Jalisco spur the economy and help the local community, which benefited from the nearly 1,000 jobs created during the construction phase, Ochoa said.




 
 
 

Donald Trump loses battle against UK wind farm

$
0
0
Donald Trump has bought a five star golf resort on the west coast of Ireland after losing a legal action against a wind farm being built near his golf resort in Aberdeenshire. The billionaire property developer said that while he appealed against the court defeat in Scotland he would be diverting his energies to the exclusive Doonbeg golf and hotel complex on the Atlantic coastline of County Clare, restyling it the Trump International Golf Links, Ireland.

Trump had taken the Scottish government to court over a decision to approve a major experimental windfarm in Aberdeen Bay, which will be about two miles south east of his planned £750m golf resort, because it spoilt the view.
He had alleged in court that Alex Salmond, Scotland’s first minister and local MSP, had secretly interfered in the decision to approve the 11-turbine site, known as the European Offshore Wind Deployment Centre, and there had been clear bias in favour of the windfarm.
He alleged in the judicial review that his own human rights had been breached, because the windfarm, which is funded by the European commission and supported by many local organisations which had also backed Trump’s golf resort, interfered with his “peaceful enjoyment of his property”.
His claims were rejected by Lord Doherty, in the court of session in Edinburgh, but Trump said from his offices in New York: “We will appeal this decision and, in the meantime, we will be focusing all of our investment and energy towards our new acquisition on the Atlantic ocean in Ireland.”
The Doonbeg resort was put up for sale earlier this year, reportedly priced at £12.4m, boosting an Atlantic seascape that stretches for 2.5 miles and a 218-room hotel with a spa and restaurants.
“Doonbeg is an already terrific property that we will make even better – it will soon be an unparalleled resort destination with the highest standards of luxury,” Trump said.
Trump has long threatened to decamp to Ireland if he was thwarted in his plans for the major hotel and golfing resort near Aberdeen, which are due to include a large five star hotel, timeshare apartments and a private housing estate.
The first 18-hole course at Menie, Aberdeenshire, opened in 2012 and Trump now has planning approval for a second course, and a major club house.
Despite admitting several years ago that the global recession had affected his plans for the resort, Trump has since insisted the expansion of the Menie estate resort was being put on hold until the windfarm scheme was dropped.
Doherty dismissed the claims that Salmond had interfered, stating he “was not persuaded that the fair-minded and informed observer would conclude that there was a real possibility of bias on the part of the decision-maker; or that the decision not to have a public inquiry had been unreasonable or unlawful.”
In a ruling with far wider significance for the future of Scottish wind power, the judge disputed a previous court ruling cited by Trump that no windfarm can be approved until or unless it had an electricity generation licence.
Planning approval for one of Europe‘s largest onshore windfarms, the huge 103-turbine Viking scheme on Shetland, was suspended in October after a judge, Lady Clark, ruled that it should not have been granted without an electricity generation licence under the Electricity Act 1989.
Her analysis, now being contested by the Scottish government, caused consternation for renewables companies and ministers since it implied that numerous windfarm applications could be legally flawed. Clark also ruled that ministers had breached the EU birds directive by failing to properly protect the whimbrel, a rare and vulnerable wading bird which is native to Shetland.
Trump sought but failed last year to become a party to the Viking windfarm appeal, to support the Sustainable Shetland anti-windfarm legal case, but used that case to justify his judicial review of the EOWDC project.
In a statement issued in New York, the Trump Organisation said: “Today’s decision has not altered our unwavering commitment to protect our investment in Scotland. We are reviewing Lord Doherty’s decision and will pursue the legal options available to us as recommended by our counsel. Communities worldwide continue to challenge the destructive proliferation of wind turbines and we will remain a fierce opponent at the forefront of this battle.
“Despite today’s decision, the EOWDC proposal has numerous economic and legal obstacles that will ultimately prevent its construction.”
The court had heard evidence from a golfing blogger and a professor of linguistics that Salmond had told him during lunch at a function that the EOWDC scheme would “absolutely” go ahead, before planning approval had been granted by Marine Scotland.
Trump also alleges that the decision not to have a full planning enquiry was improper, as it was not known what type of wind turbines would be used for the project and that different types of machine could be used at different times.
Doherty ruled that Trump’s human rights were not relevant to this case, adding that he was “satisfied that the [planning] minister had taken account of the experimental nature of the deployment centre; and that he was entitled to grant consent subject to the conditions which he imposed.”

 
 
 

Energías renovables y eólica: Donald Trump pierde batalla legal contra un parque eólico en Escocia

$
0
0
La Justicia determinó que el gobierno escocés había actuado conforme a la ley al aprobar la construcción de la central eólica, que tendrá un valor de unos cuatrocientos millones de dólares.
El empresario estadounidense Donald Trump perdió una batalla legal en Escocia, donde intentaba detener la instalación de turbinas eólicas cerca de un campo de golf de su propiedad en la ciudad de Aberdeenshire.
Trump había argumentado que arruinaría las vistas desde el campo de golf y que era un desastre para el medio ambiente.
Su campo de golf fue construido a pesar de que ambientalistas y algunos residentes de la zona se oponían, argumentando que dañaría un área de dunas de arena.


 
 
 

NREL Report Finds Similar Value in Two Concentrated Solar Power (CSP) Technologies

$
0
0
Findings demonstrate increasing importance for Concentrated Solar Power (CSP) systems with thermal energy storage.

Parabolic troughs and dry-cooled towers deliver similar value for concentrating solar power (CSP) plants, despite different solar profiles, a new report by the Energy Department’s National Renewable Energy Laboratory has found.
The report, “Estimating the Performance and Economic Value of Multiple Concentrating Solar Power Technologies in a Production Cost Model,”PDF found that the value of delivered energy of dry-cooled tower and parabolic trough CSP plants, integrated with thermal energy storage, are quite similar.
CSP with thermal energy storage is a unique source of renewable energy in that the solar thermal energy can be dispatched in a similar manner as conventional thermal generation to respond to changes in supply or demand.
CSP uses the thermal energy of sunlight to generate electricity. Parabolic troughs and power towers both concentrate sunlight onto a heat-transfer liquid, which is used to drive a steam turbine. Unlike photovoltaic energy, CSP can generate electricity not just when the sun is shining, but also after sundown, because a CSP plant can be built with thermal energy storage, such as molten salt.
“In our study, we analyzed various plant configurations and identified specific ones that provide significantly more value than has been found in previous analyses,” said NREL Analyst Jennie Jorgenson, the lead author of the report. “For example, we explored the potential benefits of extending thermal storage at CSP plants beyond six hours, a typically modelled amount. In this analysis we found additional benefits for six to nine hours of storage, but rapidly diminishing benefits for greater than nine hours of storage.”
The NREL report, funded through the Energy Department’s Office of Energy Efficiency and Renewable Energy in support of its SunShot Initiative, provides valuable quantitative results in a Colorado test system, comparing the two CSP technologies with thermal energy storage and evaluating how the operational and capacity value varies with plant configuration. The report also demonstrates that multiple CSP technologies and plant configurations can be analyzed using traditional planning tools such as production cost models.
NREL is currently undertaking a similar analysis looking at the value of multiple CSP configurations in California under an assumed 40% penetration of renewables within that state.
“For both conventional and renewable energy systems, low levelized cost of energy does not necessarily reflect these systems’ total value to the grid,” Jorgenson added. “So, providing tools that utilities and grid operators are familiar with can lead to more informed decision-making as greater levels of renewable energy penetrate the market.”
NREL is the U.S. Department of Energy's primary national laboratory for renewable energy and energy efficiency research and development. NREL is operated for the Energy Department by The Alliance for Sustainable Energy, LLC.




 
 

 

USGS releases first-ever national map of onshore wind turbines

$
0
0
Wind energy is one of the fastest-growing sectors of renewable energy in the United States.  About 3% of the total electricity in the United States was generated by wind turbines in 2012 (according to the U.S. Energy Information Administration), which is equivalent to the annual electricity use for about 12 million households.  The amount of electricity generated by wind has increased from about 6 billion kilowatt hours (kwh) in 2000 to 140 billion kwh in 2012.

In response to the Department of Interior’s Powering Our Future initiative, the U.S. Geological Survey (USGS) has begun investigating how to assess the impacts of wind energy development on wildlife at a national scale.
Assessment Experience
The USGS has extensive experience assessing energy resources, and it’s that expertise that makes the USGS qualified to assess nationwide impacts of wind energy development. One of the major reasons behind the success of USGS energy resource assessments is the scientifically robust methodology that underpins them.
USGS energy resource assessment methodologies are publicly available and are technically peer reviewed externally, and just as importantly, are used consistently in every assessment. That means that a USGS oil and gas assessment in Alaska provides comparable information to a USGS oil and gas assessment in Texas, or that a USGS geothermal assessment in California is comparable to a USGS geothermal assessment in Nevada.
A Different Kind of Assessment 
USGS has recently undertaken a project to develop a methodology for assessing wind energy impacts on wildlife at a national scale. This research is different from previous USGS energy assessments. Instead of looking at technically recoverable resources of oil, gas, geothermal or coal, or even technically accessible storage areas for carbon sequestration, the USGS is developing a method for determining the impacts of a type of energy production. This work will merge the experience the USGS has creating assessment methodologies with its expertise in wildlife ecology and wind-wildlife research, as well as in land change science.
Wind energy can impact both wildlife and their habitats. Wildlife impacts include potential bird and bat mortality from collisions with turbine blades, and in some cases, species avoidance of habitat near turbines. Habitat impacts include the turbine pads in addition to service roads, transmission lines, substations, meteorological towers, and other structures associated with wind energy siting, generation, and transmission.
Turbine Locations
The first step in understanding the impact of wind energy development is to determine where the wind turbines are located. Prior to this study, there was no publicly available national-level data set of wind turbines. There were maps that showed turbines locations  in a few states, and there were national-level maps that showed wind power facilities, but not individual turbines, or information about  those turbines, such as height, blade length, or energy producing capacity.
A screenshot of the USGS WindFarm Mapping Application, which allows users to access the more than 47,000 individual wind turbines contained within the national wind turbine database. This view shows facilities in Southern California, color-coded for their wind-generating capacity. The red and yellow turbines have a higher electricity-generating capacity than the green and blue turbines do. Click here to get started!
To remedy the lack of information, the USGS created this publicly available national dataset and interactive mapping application of wind turbines.  This dataset is built with publicly available data, as well as searching for and identifying individual wind turbines using satellite imagery. The locations of all wind turbines, including the publicly available datasets, were visually verified with high-resolution remote imagery to within plus or minus 10 meters.
Knowing the location of individual turbines, as well as information such as the make, model, height, area of the turbine blades, and capacity creates new opportunities for research, and important information for land and resource management.  For example, turbine-level data will improve scientists’ ability to study wildlife collisions, the wakes causes by wind turbines, the interaction between wind turbines and ground based radar, and how wind energy facilities overlap with migratory flyways.
Next Steps
In addition to the value this powerful tool has to Federal and State land managers, non-governmental organizations, the energy industry, scientists, and the public, it will be a useful component in the methodology that the USGS is developing for assessing wind energy impacts. The USGS is bringing together scientists with expertise in landscape-level science, wildlife biology, and other associated disciplines to create the methodology. Once developed, the methodology will be externally peer-reviewed and tested with pilot-level data projects. Once peer reviewed, the revised methodology will be published for others to understand and use.

 
 

ABB Cables To Connect 400 MW Offshore Wind Farm With UK Grid

$
0
0
High-voltage power cables to connect Dudgeon Offshore Wind Farm with UK national grid 

 ABB, the leading power and automation technology group, has won an order worth around $55 million to supply a submarine AC (alternating current) power cable system for a new wind farm, located off the coast of Norfolk. The underwater cables will feed the electricity generated by the 400-megawatt (MW) Dudgeon Offshore Wind Farm into the UK national grid. The order was received from Dudgeon Offshore Wind Limited, a company owned by Statoil and Statkraft.
The Dudgeon Offshore Wind Farm will be capable of producing enough electricity to power more than 400,000 UK homes annually. The turbines will be located in waters 18-25 meters deep on a 55-square-kilometer site situated 32 kilometers (km) off the coast of the seaside town of Cromer in north Norfolk. With an installed capacity of about 400 MW, the wind farm will produce enough ‘green’ energy to displace emissions of carbon dioxide by up to 19 million tonnes over its 25-year lifetime.
Electricity generated by the wind farm will be brought to shore via a seabed cable at Weybourne Hope, some 5 km west of the coastal town of Sheringham. From there, an underground cable will be laid to carry the electricity to Necton, where a purpose-built substation will enable it to be transmitted into the national grid. 
“Offshore wind is a growing renewable energy resource, with Europe accounting for around 70 percent of new offshore wind generation capacity. Transporting electricity from offshore wind farms to the shore and then integrating it into the grid for supply to consumers are key elements,” said Claudio Facchin, Head of ABB’s Power Systems division. "This is a key focus area for ABB as we strive to balance the growing need for electricity while minimizing environmental impact. Our technological strengths, vast portfolio and rich experience in this area position us well to execute this project and we are delighted to have this opportunity.”
ABB will design and supply two 132-kilovolt (kV) three-core AC submarine cables, each 42 km in length, running from the wind farm’s offshore substation to Weybourne Hope, where they will connect to the onshore cables. The submarine cables will be manufactured at ABB’s high-voltage cable factory in Karlskrona, Sweden, and delivery will commence in 2016.
“The submarine export cable connection is a long-lead item and placing this contract represents a major milestone in the development of the Dudgeon project,” said Bjørn Ivar Bergemo, Asset Manager of the Dudgeon Offshore Wind Farm. “These cables will be some of the longest offshore cables ordered so far for a UK offshore wind project, and we look forward to working with ABB.” 

 
 
 

El Nissan Leaf es el vehículo eléctrico más vendido de Europa

$
0
0
El Nissan Leaf se consolida en el mercado de los vehículos eléctricos. El coche eléctrico utilitario japonés ha conseguido ser el vehículo eléctrico más vendido en toda Europa durante el último año.

 
Con una cuota del 33% de las ventas de coches eléctricos en Europa, el Leaf vendió, en 2013, más de 5.600 unidades más que el año anterior y consolidó así su posición como el coche totalmente eléctrico más vendido del Mundo, aumentando un 204% respecto al año 2012.

El éxito de este modelo es debido en una parte muy importante a un sólo país, Noruega, donde es tan popular como vendido. Aún así, también fue el eléctrico más vendido en España, Italia, Dinamarca, Suecia, Portugal, Finlandia, Bélgica y Gran Bretaña.

Significativo ha sido el aumento porcentual interanual (2012-2013) de ventas tanto en Gran Bretaña como Francia. En el país isleño el crecimiento ha sido nada más y nada menos que de un 1000%. En Francia, también han experimentado un 240% de crecimiento.

En España, aún no es tan vendido como en otros países europeos, pero el Nissan Leaf es sin duda un referente en su mercado en nuestro país. Cabe recordar que además este modelo fue nombrado el Mejor Coche del Mundo en 2011.

 
 
 

Energía solar y energías renovables: Alberto Fabra inaugura en Villena la central termosolar

$
0
0
En octubre de 2013 concluyó la fase de instalación de colectores en el campo solar, iniciando entonces la termosolar su actividad industrial.

El presidente de la Generalitat Valenciana, Alberto Fabra, asistirá hoy en Villena a la inauguración de la central  de energía solar termoeléctrica, ubicada en el paraje de Los Alhorines.
En octubre de 2013 concluyó la fase de instalación de colectores en el campo solar, iniciando entonces la termosolar su actividad industrial.
La central termosolar de Villena, la única de estas características en la Comunidad Valenciana y la más moderna de las 60 construidas hasta el momento en España, ha comenzando a inyectar en la red eléctrica parte de los 49,9 megavatios que va a generar, y que Iberdrola se está encargando de comercializar.
Una potencia con la que se podría abastecer a una ciudad de 35.000 habitantes, del tamaño de Villena por ejemplo, y que se logra sin ninguna emisión de gases a la atmósfera.
La termosolar genera únicamente vapor de agua porque en las termosolares la única fuente de energía es el sol, cuya radiación calienta el aceite que circula por unos colectores para producir el vapor de agua que, a su vez, se encarga de mover una turbina que acciona un generador. Y de ahí surge la electricidad.
Los trabajos para construir este complejo que ocupa una superficie de 120 campos de fútbol, en los que la UTE Termosolar Villena FCC Industrial y Seidor ha invertido 200 millones de euros, han finalizado antes de lo previsto.
Las obras arrancaron en julio de 2010 y en la ejecución del proyecto han participado más de 500 obreros. De todos ellos son 50 los puestos directos de trabajo que ya se han creado para dirigir y mantener la instalación con el apoyo de 30 indirectos.
Este equipo, del que forman parte diez ingenieros técnicos, superiores e industriales y un químico, se está encargando de supervisar el correcto traspaso de energía desde la planta hasta la red eléctrica. El proceso finalizará dentro de un mes cuando la subestación que Iberdrola ha construido junto a la termosolar reciba los 49,9 megavatios de potencia total instalada. Una energía limpia y renovable que 141.200 espejos se encargan de extraer del astro rey para beneficio de los hombres.



 
 
 

Unas 20 empresas buscan licitar los 100 MW de energías renovables en El Salvador, 40 MW de eólica y 60 MW de energía solar fotovoltaica

$
0
0
La licitación de El Salvador busca generar energías renovables. Hay propuestas de proyectos eólicos y de energía solar fotovoltaica. Unas 20 empresa han comprado las bases para la licitación del suministro de los 100 megavatios (MW) de potencia, y su energía asociada, que esperan contratar las distribuidoras del país.

Luis Reyes, secretario ejecutivo del Consejo Nacional de Energía (CNE), dijo que la licitación ha despertado interés de empresas nacionales, pero que también hay inversionistas internacionales que esperan participar en esta nueva licitación.
“Hay empresas de diferentes países, hay españolas, italianas, alemanas y también salvadoreñas. Las empresas están muy interesadas en esta licitación. Hemos recibido bastantes consultas por parte de las empresas”, indicó Reyes.
El suministro de los 100 MW se contratará dividido en dos tecnologías de generación: 60 MW serán destinados para generación con sistemas fotovoltaicos o energía solar y 40 MW con recursos del viento o energía eólica.
El contrato de suministro se firmará para un plazo de 20 años, a partir de 2016 para los generadores con recursos solares y desde 2017 para los que decidan instalar sistemas eólicos.
Reyes dijo que el plazo para que las empresas compren las bases y participar en la licitación está por agotarse.
“El viernes (14 de febrero) es el último día para comprar las bases de licitación. Después viene una semana en la que les vamos a responder (a los inversionistas) las últimas preguntas que lleguen, y ellos van a tener que ofertar”, apuntó el funcionario.
El representante del CNE indicó que cerca del 80 % de los inversionistas se ha decantado por los proyectos de energía solar para el suministro y la generación; sin embargo, existe un 20 % de ellos que está interesado en instalar sistemas eólicos.
“Nosotros creíamos que solamente iban a haber ofertas de fotovoltaicas, pero la verdad que también hay empresa que van a participar con ofertas eólica”, señaló Reyes.
Según el calendario del CNE, la entrega de oferta técnica y económica por parte de la empresa será el 31 marzo de 2014, y la firma de contrato el 29 de mayo.
Se espera que la licitación genere en los próximos años una inversión que rondará los $200 millones.


 
 


Wind power: Vestas secures 84 MW service agreement with an option for up to 150 MW in Romania

$
0
0
Vestas has secured a 15-year service contract covering 42 V90-2.0 MW wind turbines at the Topolog Dorobantu wind power plant in Tulcea County in Romania.

The last of the 42 wind turbines is expected to be installed within April this year. The order has been placed by LUKERG Renew, a joint venture between ERG Renew and LUKOIL. ERG Renew is Italy’s largest wind energy producer, with an installed capacity of 1,340 MW throughout Europe. LUKOIL is a major international vertically-integrated oil and gas company, accounting for 2.2 per cent of global output of crude oil.
The agreement is based on Vestas’ Active Output Management (AOM) 5000, which offers an energy-based availability guarantee that ensures the turbines are operational when the wind is blowing. This service option includes the VestasOnline® surveillance system that remotely controls and monitors the turbines. This makes it possible to conduct preventative maintenance that minimises turbine downtime. Topolog Dorobantu wind power plant will be the first project in Romania benefiting from this new service platform.
We are pleased to receive this service order with an option for up to 150 MW wind power plants from our highly valued customer LUKERG Renew. We are happy to support our customer’s business case with our 30 years of wind energy experience and modern Active Output Management service package”, says Mikael Rönholm-Nielsen, Vice President Sales, Austria/Eastern Europe. “This contract underlines LUKERG Renew’s confidence in our expertise and in our capability to provide the optimal service for their large wind power plants in an important market such as Romania.”
The Topolog Dorobantu project is one of the largest projects in Romania and produces more than 200 GWh per year, which corresponds to an annual saving of almost 110,000 tons of CO2 emissions. Furthermore, it provides enough electricity to cover the residential electricity consumption of more than 60,000 Romanian households.
Every single day, Vestas wind turbines deliver clean energy that supports the global fight against climate change. Wind power from Vestas’ more than 51,000 wind turbines currently reduces carbon emissions by over 60 million tons of CO2 every year, while at the same time building energy security and independence. Today, Vestas has installed turbines in 73 countries, providing jobs for around 16,000 passionate people at our service and project sites, research facilities, factories and offices all over the world. With 62 per cent more megawatts installed than our closest competitor and more than 60 GW of cumulative installed capacity worldwide, Vestas is the world leader in wind energy.
The headquarters of Vestas Central Europe is located in Hamburg, Germany. The business unit is responsible for the sales and marketing of wind power systems as well as for the installation and operation of  wind power plants in Germany, Benelux, Austria, Russia, Eastern Europe and Southern and Eastern Africa.
Vestas entered the Romanian market in 2008 and is now the market leader here, with headquarters in Bucharest as well as several working sites in the field for construction and service activities. The local economy benefits greatly from wind energy’s ability to drive economic growth; skilled jobs are created also in remote areas and around 60 per cent of the revenues generated through the lifetime of a modern 3 MW wind power plant go to local construction companies, suppliers, service providers and communities.


Acciona podría afrontar un impacto de 1.900 millones al ajustar su cartera eólica

$
0
0

Acciona podría afrontar en sus cuentas de 2013 un impacto de entre 1.800 y 1.900 millones de euros derivado del ajuste de valor de sus activos de energías renovables, fundamentalmente de los parques eólicos, que se verán afectados por el recorte de retribución impuesta por la reforma energética aprobada por el Gobierno.

 

Así lo estima la firma de analistas Fidentiis, que calcula que el 77% de los activos eólicos del grupo que preside José Manuel Entrecanales en España, aquellos construidos antes de 2008, sufrirán disminuciones de las primas.
No obstante, los parques que experimentarán un mayor recorte son los anteriores a 2005, que en el caso de Acciona copan el 37% de todas sus instalaciones eólicas en España.
Ello a su vez tendrá un impacto en el beneficio bruto de explotación (Ebitda) de la compañía de unos 200 millones de euros, según indica un informe de esta firma de análisis.
Por contra, Fidentiis descarta que este impacto tenga efecto en la estabilidad financiera del grupo de construcción, servicios y renovables, y en su endeudamiento, dado que la reforma energética afecta principalmente a los activos más maduros y, por ende, con menor pasivo.
No obstante, los analistas apuntan a la posibilidad de que surja algún problema con las condiciones del préstamo sindicado de 1.400 millones de euros que Acciona firmó en 2011 para comprar activos de 'energía verde' de Endesa.
Acciona es uno de los principales promotores y operadores de instalaciones de energía verde del mundo. A cierre de septiembre de 2013, contaba con un total de 8.500 megavatios (MW) de instalaciones renovables instalados, de los que 4.073 MW constituyen parques eólicos instalados en España.
La compañía está a la espera de que se concrete definitivamente la última fase de la reforma energética, la aprobada en julio de 2013, para calcular el impacto total de las modificaciones en sus cuentas.
Por el momento, los dos cambios normativos aprobados con anterioridad a dicha fecha y ya en vigor generaron un impacto de 131 millones de euros en las cuentas de Acciona hasta de septiembre, importe equivalente al 84% del beneficio bruto de explotación (Ebitda) que genera toda su división de energía y el 63% del de todo el grupo.
Con el fin de mitigar estos efectos, el grupo lanzó en marzo del pasado año un plan de ajuste que entre, otras medidas, incluye ventas de activos, un recorte de inversiones, buscar socios financieros para desarrollo de proyectos y contención de costes. Además, Acciona ha suspendido por vez primera el pago de su dividendo a cuenta.

 
 

Sena formará técnicos en energía solar fotovoltaica en Colombia

$
0
0
La meta es capacitar más de 400 expertos en energías renovables en los próximos años, con las centrales donadas por Alemania. El Servicio Nacional de Aprendizaje (Sena) entrará a valorar las diferentes tecnologías que existen actualmente en el mercado de paneles fotovoltaicos, para establecer cuáles son las que más se adaptan a las regiones colombianas, según sus condiciones meteorológicas y de radiación solar e igualmente comenzará a ofrecer un programa de formación sobre sistemas de energía solar.

Para lograr esto, jugó un papel importante el convenio que firmó con la empresa Sunset−Solar, en septiembre del 2012, el cual dio origen al proyecto ‘Sunsena’, con el que estas dos entidades unieron sus esfuerzos para promover las fuentes alternativas en Colombia.
Sunsena comprendió varias estrategias, la primera fue la instalación de dos plantas fotovoltaicas con una capacidad de 20 kilovatios−pico (Kwp), cada una en igual número de instalaciones del Sena, con fines demostrativos y de formación.
Una de estas unidades está ubicada en la sede del Centro de Electricidad, Electrónica y Telecomunicaciones (Ceet) de Bogotá y la otra en el Centro Regional, en Puerto Carreño, Vichada.
“Con ellas esperamos evaluar el desempeño que tendrán según las circunstancias atmosféricas de estas dos ciudades, lo cual se podrá hacer gracias al sistema de monitoreo online de que disponen, el cual medirá la radiación solar, la temperatura, la velocidad del viento y la cantidad de energía que generan diariamente”, indica Marco Polo Nempeque, líder del Área Temática de Energías Renovables del Sena.
La información que se obtenga de estas observaciones permitirá a las entidades oficiales del sector energético tomar a futuro, las decisiones más adecuadas sobre cuáles de los diferentes tipos de paneles solares que se colocaron en estos sitios son los más óptimos para ser acoplados en las diferentes zonas del país.
“Para establecer estos factores, en el Ceet se situaron cuatro clases de módulos solares como son el monocristalino, capa fina o Amorfo, policristalino y especiales con células de alto rendimiento”, observa Nempeque.
TRANSFERENCIA DE CONOCIMIENTO
El otro componente que incluyó esta iniciativa es la transferencia de conocimiento, por eso se capacitaron a cerca de 25 multiplicadores entre instructores del Sena e ingenieros de diferentes empresas, sobre diseño, planificación, instalación, manejo y mantenimiento de módulos solares.
La formación que recibieron estas personas por parte de los expertos de Sunset−Solar, será empleada por el Sena, para empezar a ofrecer en el 2014 un programa de formación de técnicos electricistas con competencia para instalar sistemas de energía solar fotovoltaica.
Quienes se inscriban en este curso saldrán capacitados para realizar un montaje de estos, ponerlo en marcha y realizarle luego el mantenimiento necesario.
“Como los programas de formación para técnicos en el Sena tienen una duración de un año y medio, esperamos capacitar a más de 400 aprendices en los próximos años, con las plantas recibidas de la donación del programa develoPPP de Alemania, donde participaron (Sunset, Iseep y QES), de este modo se complementa la infraestructura existente en otros centros para ofrecer instrucción en energía solar”, dice Nempeque.
La energía que genere la unidad que se ubicó en el Ceet servirá para atender la demanda de electricidad que necesite este lugar para su funcionamiento.
La planta fotovoltaica está estimada para que produzca 31.600 kilovatios/año de energía, por tanto, esto le generará a esta sede un ahorro en el consumo de electricidad de unos 15 millones de pesos anualmente.
“La vida útil de este sistema que inyectará energía a la red durante 10 horas (sistema on− grid) será de unos 40 años”, indica Dominik Hammer, gerente de cuentas internacionales de Sunset−Solar.
Entre tanto, el proyecto que se instaló en Puerto Carreño − Vichada, será un sistema híbrido de almacenamiento y de inyección de energía eléctrica a la red de este Centro Regional, con lo cual el Sena entra a promover el uso de fuentes alternativas en el país. El proyecto Sunsena, fue cofinanciado por el Ministerio Alemán de Cooperación Económica y Desarrollo (BMZ), que aportó 193 mil euros, por Sunset Energitechnik GmbH, con 225.068 euros y el Sena que colaboró con adecuaciones físicas, logísticas y otros gastos. Además contó con la ayuda de las consultoras QES de Colombia e Iseep de Alemania.



 
 

U.S. Utility-Scale Solar Power 60 Percent Towards Cost-Competition Goal

$
0
0
The Energy Department announced today that the U.S. solar industry is more than 60 percent of the way to achieving cost-competitive utility-scale solar photovoltaic (PV) electricity – only three years into the Department’s decade-long SunShot Initiative. To help continue this progress, the Energy Department also announced today $25 million in funding to strengthen U.S. solar manufacturing for photovoltaic and concentrating solar power (CSP) technologies and to maintain a strong domestic solar industry – supporting the Department’s broader Clean Energy Manufacturing Initiative. 
 
In the State of the Union address, President Obama highlighted the United States’ growing role as a global leader in solar as demonstrated in a new industry report which recently found that U.S. utility-scale solar set a record with 2.3 gigawatts installed in 2013. Tomorrow, Energy Secretary Ernest Moniz will travel to Ivanpah Dry Lake, Calif., to dedicate the world’s largest concentrating solar power plant – continuing U.S. leadership in clean energy.
“In just the last few years, the U.S. has seen remarkable increases in clean and renewable energy – doubling the amount of energy that we produce from solar and wind and supporting a strong, competitive solar supply chain that employs American workers in every state,” said Energy Secretary Moniz. “To continue this growth and position the U.S. as a global leader in clean energy innovation, the Energy Department is helping to advance new technologies that further reduce costs, improve performance and support new jobs and businesses across the country.”
Utility-Scale Photovoltaic 60 Percent Towards Meeting SunShot Goal
In 2011, the Energy Department launched its SunShot Initiative to make solar energy cost-competitive with traditional energy sources by the end of the decade. Through partnerships with industry, universities, local communities and the Department’s national laboratories, the SunShot Initiative is working aggressively to drive innovation and lower the cost of solar energy – from more efficient, high-performing solar modules to streamlined permitting, installation and interconnection processes.
Today, the utility-scale PV industry is more than 60 percent of the way to achieving SunShot’s target of $0.06 per kilowatt-hour. In the United States, the average price for a utility-scale PV project has dropped from about $0.21 per kilowatt-hour in 2010 to $0.11 per kilowatt-hour at the end of 2013. According to the Energy Information Administration, the average U.S. electricity price is about $0.12 per kilowatt-hour. Check out a new Energy.gov graph that shows how these costs have fallen in just the last three years.
Reductions in the cost of electricity are based on estimates of the levelized cost of electricity (LCOE). The LCOE is a measure of the national average of electricity cost based on certain assumptions regarding financing costs and generation availability projected over the life of a generating asset. The LCOE model provides a benchmark for measuring relative changes in electricity costs.
During President Obama’s first term, the United States more than doubled generation of electricity from wind, solar and geothermal sources, and installed solar capacity has grown ten-fold from 1.2 gigawatts in 2008 to an estimated 13 gigawatts today. To ensure America’s continued leadership position in clean energy, the President has set a goal to double renewable electricity generation once again by 2020.   
$25 Million to Boost U.S. Solar Manufacturing
Over the last three years, the cost of a solar energy system has dropped by more than 50 percent – helping to give more and more American families and businesses access to affordable, clean energy. Today, the Energy Department announced $25 million in new funding to boost domestic solar manufacturing and speed up the commercialization of efficient, affordable PV and CSP technologies. This funding opportunity will help to further lower the cost of solar electricity, support a growing U.S. solar workforce and increase U.S. competitiveness in the global clean energy market.
This new SunShot funding opportunity will support innovative projects that help solar manufacturers tackle key cost-contributors across the hardware supply chain and make improvements in a broad range of manufacturing processes that save time and money. Eligible projects may include developing advanced technology that lowers domestic solar manufacturing costs and developing and demonstrating components or new manufacturing processes that cut project construction and installation time. Find more information on the Solar Manufacturing 2 funding opportunity, including application requirements, HERE.
The Energy Department’s SunShot Initiative aims to make solar energy fully cost-competitive with traditional sources of energy by 2020. 

 
 
 

Energía geotérmica por magma

$
0
0
En 2009, una perforación realizada en Krafla, en el noroeste de Islandia, como parte de un proyecto islandés de prospección (IDDP), penetró inesperadamente en una zona de magma (roca fundida) a sólo 2.100 metros de profundidad, con una temperatura de 900 a 1.000 grados centígrados. La perforación, IDDP-1, fue la primera en una serie de pozos que están siendo excavados por el IDDP en Islandia en busca de fuentes geotérmicas de alta temperatura.


Cinco años después de aquel acontecimiento es un buen momento para revisar qué se ha hecho desde entonces y cuáles son las perspectivas futuras de esta inesperada y valiosa fuente de energía.

Perforar hasta alcanzar el magma es un suceso muy poco frecuente en cualquier parte del mundo, y, que se sepa, ésta es sólo la segunda vez que ha ocurrido, siendo la primera en 2007, en Hawái. Los responsables del proyecto IDDP decidieron investigar más el pozo y sufragar parte de los considerables costos implicados.

Así pues, se instaló una estructura especial de acero en el pozo, muy cerca del magma, y se dejó entonces que el pozo se calentara lentamente. Al final se permitió que fluyera vapor supercaliente durante los siguientes dos años, hasta julio de 2012, cuando el pozo se cerró para poder reemplazar parte del equipamiento de superficie.

En el futuro, el éxito de este proyecto de investigación podría llevar a una revolución en la eficiencia energética de las zonas geotérmicas de alta temperatura de todo el mundo.

Se consiguieron varios avances importantes en este proyecto: A pesar de algunas dificultades, se pudo perforar hasta el magma y controlarlo; fue posible instalar la citada estructura de acero en el tramo más hondo del pozo; y el chorro de vapor de alta presión a temperaturas de más de 450 grados centígrados batió un récord mundial de calor geotérmico (este pozo fue el más caliente del mundo y uno de los más potentes; siglos atrás no habría faltado quien lo considerase la mismísima boca del infierno); el vapor del pozo IDDP-1 puede ser inyectado directamente en la planta energética de Krafla; y el IDDP-1 demostró que se puede utilizar con éxito un sistema geotérmico de muy alto rendimiento.
En esencia, el IDDP-1 permitió instalar el primer sistema geotérmico mejorado con magma del mundo. Este sistema geotérmico preparado de forma única es el primero en suministrar calor directamente desde el magma fundido.

En varias partes del mundo, los sistemas de energía geotérmica mejorada deben esas mejoras a una gran presencia de componentes artificiales adicionales. Lo más común es bombear agua fría dentro de rocas calientes a profundidades de 4 ó 5 Km. En décadas recientes, se ha invertido un considerable esfuerzo en Europa, Australia, Estados Unidos y Japón, pero sus resultados, aunque interesantes, obviamente no pueden competir con los del sistema creado en IDDP-1, que parte de la ventaja natural de contar con magma a tan solo 2.100 metros de profundidad.

Una de las próximas etapas del proyecto será excavar otro pozo, el IDDP-2, en un punto ubicado en el sudoeste de Islandia, entre este año y el 2015.

El proyecto IDDP es una colaboración entre tres empresas del sector energético y un organismo gubernamental de Islandia.

Desde el principio, la colaboración internacional ha sido importante para el proyecto, y en particular se ha mostrado muy activo un consorcio de científicos estadounidenses, coordinados por Wilfred Elders, profesor emérito de geología en la Universidad de California en la ciudad estadounidense de Riverside.

 
 
Viewing all 10409 articles
Browse latest View live