Quantcast
Channel: José Santamarta Flórez
Viewing all 10308 articles
Browse latest View live

China's installed capacity for grid-connected wind power rose nearly 26 percent to 96.37 gigawatts in 2014

$
0
0
The nation is on track to meet a wind energy capacity target of 100 GW set in its 2011-2015 "five-year plan" for the energy sector after a rapid construction programme and a concerted effort to make sure new projects are connected to the grid.


China's installed capacity for grid-connected wind power rose nearly 26 percent to 96.37 gigawatts (GW) in 2014, accounting for 7 percent of the country's total, the National Energy Administration said on Thursday.

The administration said in a statement on its website (www.nea.gov.cn) that newly added wind capacity in 2014 hit a record 19.81 GW. A total of 77 GW is now under construction.Total wind power generation reached 153.4 billion kilowatt hours (kWh) in 2014, 2.78 percent of the total, it said.
The administration said last month that China's total power capacity reached 1,360 GW by the end of last year, up 8.7 percent on the previous year. Total generation stood at 5.523 trillion kWh, up 3.8 percent.

http://www.evwind.es/2015/02/12/chinas-installed-capacity-for-grid-connected-wind-power-rose-nearly-26-percent-to-96-37-gigawatts-in-2014/50441



Ethiopia eyes investing on 300 MW wind energy

$
0
0
Ethiopia is in negotiations to finalize a deal with a Chinese firm Dongfang Electric Corporation to construct a 120 MW wind farm in place called Ayisha near the Djibouti Border.

Miskir Negash, External Communications Director at Ethiopian Electric Power (EEP), told newBusinessEthiopia.com that with the country embarking on a green economy strategy, wind power is one key component.
“while our main focus in on hydro electricity generation, we’re also seeing other options prominent among them being wind, and as such we’ve inaugurated so far 171 MW of wind energy” stated Negash adding that Ayisha project is estimated to have a current power generation capacity of 300MW.
Ethiopia has so far managed to commission two wind power projects built by French and Chinese firms respectively in the northern and central part of the country.
The first project to be commissioned the 51 MW Adama I wind power project, 95 kms south east of ethiopia’s capital Addis Ababa, constructed jointly by Hydro China and CGOC at a cost of $117 million and completed in 2012. 
85 percent of the project’s funding was from the China Export Import Bank while the rest 15 percent was solicited from local sources. 
The two companies have subsequently started construction on 153 MW Adama II wind power project, with according to Negash the project 82 percent complete and set to be finished this year. 
The wind farm has a budget of USD 345 million and has reached 82 percent completion rate. 85 percent of the total cost is covered by the Chinese Exim Bank, while the Ethiopian government pays for the rest.
The second project to be commissioned the 120 MW Ashegoda wind farm located in Northern part of the country was inaugurated in October 2013.
The Project costing $ 289.7 million was built by French firm Vergnet SA with concessional loans from BNP Paribas and the French Development Agency (AFD). The Ethiopian government covered 9 percent of the cost.  
Germans showing interest
Negash who refused to put an exact figure on the project said funding for the project is being looked in local and international financial sources, although the Ethiopian government estimates the total 300 MW project will need $ 536.6 million1. 
He also stated that power generation ranging from 120-300 MW in total is under discussion with a German firm Laphto Technology Private Limited Company (PLC), potentially breaking the mold with projects that are increasingly being dominated by Chinese firms. The Ethiopian government has aims for the Aysha wind farm project to eventually be able to generate up to 1,000 MW of wind energy eventually.
“Ethiopia is embarking on a second phase of its five year Growth and Transformation Plan (GTP) starting from late 2015, and the Aysha project, will be part of the plan” Negash stated before surmising that there are other projects in the pipeline like the 100 MW Assela wind farm project. 
The GTP a brainchild of the late Ethiopian Prime Minister Meles Zenawi launched in 2010 envisages Ethiopia achieving power generation capacity of 10,000 MW or more at utmost five years time from the current 2,200 MW.
The majority will come from Hydro energy, followed by wind power, Geothermal, with small contribution from waste energy and co-generation. 
The Country also hopes for the renewable energy projects, to being a much needed hard currency by way of power exports to neighboring and regional countries. 
Ethiopia so far has started limited power exports to Djibouti and Sudan of 60 and 100 MW each. It has also signed power export deal with Kenya to export electricity reaching 400 MW by 2016, as well as signed a Memorandum of Understanding with South Sudan.
The country which has invested heavily in renewable projects as part of its green economy strategy hopes to partially achieve its 2025 goal of net zero carbon emission, with investments in clean, renewable energy like wind, hydro and geothermal.  

http://www.evwind.es/2015/02/12/ethiopia-eyes-investing-on-300-mw-wind-energy/50443 



Wind energy can help U.S. meet EPA Clean Power Plan

$
0
0
Adding wind power can help the U.S. meet the Environmental Protection Agency’s (EPA) Clean Power Plan by cutting carbon pollution while keeping the lights on. That’s according to a new report released today by the American Wind Energy Association (AWEA) that explains how wind energy is already making critical contributions to the reliable operation of the power system.

“Americans want energy security, clean air, and a more reliable energy system,” said AWEA CEO Tom Kiernan. “Diversifying our energy mix with wind helps us achieve all of these goals at once.”
The 15 most common questions about wind power and reliability are answered in AWEA’s report, “Wind energy helps build a more reliable and balanced electricity portfolio,” based on grid operators’ real-world experience integrating wind power as well as dozens of studies conducted by grid operators examining how higher levels of wind use can be achieved.
As wind energy has grown to provide a larger share of our electricity mix, wind turbine technology has matured so that modern wind plants are able to provide the same grid reliability services as conventional generators.
Changes in wind output are not a major issue for grid operators because all power plants are already backed up by all other power plants, and grid operators already deal with large fluctuations in electricity supply and demand. In fact, the gradual and predictable changes in wind power are also much easier for grid operators to address than the large-scale outages that can occur at conventional power plants.
“Based on grid operators’ experience with reliably and cost-effectively integrating very large amounts of wind energy, wind can play can play a key role in meeting EPA’s Clean Power Plan,” said AWEA Senior Director of Research Michael Goggin.
Past real-world examples presented in the report help illustrate wind’s role in keeping the lights on. Wind energy helped keep the lights on in Texas when fossil-fired power plants failed in the cold in February 2011, and more recently did so again across much of the U.S. during the “Polar Vortex” in early 2014.
Other highlights of the report include:
  • Iowa and South Dakota reliably produce more than 25 percent of their electricity from wind power; nine states produce more than 12 percent and more than 4 percent in the U.S. overall.
  • Technological advances have enabled U.S. wind farms to set generation records as a percent of demand over the past two years, all without reliability problems:
    • At times more than 60 percent on Xcel Energy’s Colorado power system;
    • Nearly 40 percent of generation in ERCOT, the main Texas power system; and
    • 33 percent in the Southwest Power Pool (area that covers all or parts of several states in the Southwest
    • The largest grid operator in the U.S., PJM, recently reported it could reach 30 percent of wind power while maintaining electricity reliability.
    • Ireland, Spain, and Portugal obtaining around 20 percent of their electricity from wind on an annual basis, Denmark at nearly 35 percent, and Germany at 25 percent from wind and solar.
    • More than a dozen wind integration studies by U.S. grid operators and others find wind energy can reliably supply at least 20-30 percent of U.S. electricity demands; some studies showing 40 percent.
    • Wind power saved consumers $1 billion over just two days across the Great Lakes and Mid-Atlantic states during the 2014 “Polar Vortex” event.
    • The current U.S. wind fleet will reduce CO2 emissions by 150 million short tons per year, the equivalent of reducing power sector emissions by more than 5 percent, or 28 million cars worth of carbon emissions.
    • There’s enough wind power installed to provide electricity for the equivalent of 18 million American homes.
Last year, the EPA released its first-ever draft rules aimed at reducing carbon pollution at existing power plants. Continuing to add wind energy to the U.S. electricity mix can help comply with other parts of EPA’s plan, lessening the requirements on other parts of the electric sector.
AWEA will be testifying at FERC’s February 19 technical conference on Clean Power Plan reliability and infrastructure implications.
Policy certainty is needed so that the U.S. can continue rapidly scaling up wind power. The renewable energy Production Tax Credit has successfully helped the U.S. become the number one wind energy producer in the world. Congress must rapidly extend the PTC for the longest possible time to avoid pushing American wind power off a cliff. A loss of $23 billion to our economy and nearly 30,000 well-paying jobs resulted the last time wind was left without policy stability.
Wind power’s costs have dropped more than 50 percent over the past five years, thanks to the productivity and innovation that are driven by performance-based incentives like the renewable energy Production Tax Credit.
According to Wind Vision, a new Department of Energy report due for release in early 2015, wind could double from today’s amount to reliably supply 10 percent of the nation’s electricity demand by 2020, 20 percent by 2030 and 35 percent by 2050.
The PowerPoint presentation used for today’s webinar and report can be found here: http://bit.ly/1CZz9cA.  
A two-page fact sheet can be found here: http://bit.ly/1zaLpRq.


 
 

Mainstream Renewable Power financia su eólica en Sudáfrica

$
0
0
Mainstream Renewable Power, compañía global especializada en energía eólica y solar, anuncia hoy la exitosa concreción de un cierre financiero para tres parques eólicos en Sudáfrica con una capacidad combinada de 360 megavatios. Los parques eólicos, todos ubicados en la Provincia Septentrional del Cabo, en Sudáfrica, representan una inversión de aproximadamente USD760 millones, y se estima que la construcción comenzará este mes.

La deuda para los proyectos ha sido coordinada y asegurada por Barclays y el Development Bank of Southern Africa. El consorcio de Murray & Roberts y Conco ha sido elegido como contratista para la construcción, y Siemens Wind proveerá e instalará las turbinas eólicas. Simmons & Simmons y Bowman & Gilfillan actuaron como Asesores Legales de los Prestamistas. Fasken Martineau y Stoel Rives actuaron como Abogados del Financista.
En 2011, a un consorcio de Mainstream también se le asignaron proyectos de energía solar y eólica de 238 megavatios en el primer Programa de Adquisiciones (Procurement Programme) del Gobierno Sudafricano, y los tres proyectos están ahora operando comercialmente.
Barry Lynch, Director Gerente de Adquisiciones, Construcción y Operaciones Nacionales de Mainstream, dijo: "Mainstream ha obtenido más megavatios que ningún otro Desarrollador en el marco del Programa de Adquisiciones de Energía Renovable (Renewable Energy Procurement Programme) del Gobierno Sudafricano. Entre las Rondas 1 y 3 se nos han asignado seis proyectos con una capacidad combinada de casi 600 megavatios".
Añadió: "A nivel global, Mainstream continúa con su pujante programa de expansión: tenemos cientos de megavatios en construcción y operación en Irlanda, Chile, Canadá y Sudáfrica. Pronto implementaremos la construcción de proyectos adicionales en Chile, y recientemente hemos recibido la autorización para construir y operar dos parques eólicos multi-trillonarios en el extranjero, en Reino Unido".
Los parques eólicos que han alcanzado el cierre financiero son:
  • Khobab - 140MV
  • Loeriesfontein 2 - 140MV
  • Noupoort - 80MV
Los miembros accionarios del consorcio son:
  • Mainstream Renewable Power.
  • Actis, a través de su Actis Energy 3 Fund, un importante inversor del sector energético en mercados emergentes.
  • Thebe Investment Corporation, una de las compañías integrales de administración más consolidadas de BEE Investment de Sudáfrica (asesorada por Bridge Capital).
  • El IDEAS Managed Fund, administrado por Old Mutual Investment Group, uno de los principales administradores independientes de África.
  • Futuregrowth Asset Management, importante inversor en activos de desarrollo.
  • Genesis Eco-Energy en sociedad con Lereko Metier Sustainable Capital. 
  • Miembros de la comunidad local a través de fideicomisos comunitarios consolidados. 

 
 

Mainstream completes financial close for three wind power farms in South Africa

$
0
0
Global wind and solar company Mainstream Renewable Power today announces the successful completion of financial close for three wind farms in South Africa with a combined capacity of 360 megawatts. 

In October 2013 a consortium led by Mainstream was awarded the contracts for the three wind farms by the Department of Energy in South Africa under the third round of its Renewable Energy Procurement Programme. The wind farms, which are all located in South Africa’s Northern Cape Province, represent an investment of approximately ZAR 9 billion and are expected to commence construction this month.In 2011 a Mainstream consortium was also awarded 238 megawatts of wind and solar projects in the first round of the South African Government’s Renewable Energy Procurement Programme and all three projects are now in commercial operation.


Commenting on the announcement, Barry Lynch, Mainstream’s Managing Director, Onshore Procurement, Construction and Operations said: “The team here at Mainstream is delighted with our success today. Mainstream has been awarded more megawatts than any other Developer under the South African Government’s Renewable Energy Procurement Programme. Between Rounds 1 and 3 we have been awarded six projects with a combined capacity of nearly 600 megawatts. We are delighted to have recently delivered three wind and solar farms from Round 1 into commercial operation on budget and once again we are working with many of the same debt and equity partners, construction contractors and turbine supplier. Partnerships are very important for us and our success in South Africa is a great example of this.”
He continued: “Globally, Mainstream continues its aggressive wind and solar expansion programme; we have hundreds of megawatts in construction and operation in Ireland, Chile, Canada and of course South Africa. We are close to putting additional projects into construction in Chile in the coming months and recently received consent to build and operate two multi-billion pound offshore wind farms in the UK.”
The South African wind farms that have reached financial close are:
• The 140MW Khobab Wind Farm located in the District Municipality of Namakwa in the Northern Cape.
• The 140MW Loeriesfontein 2 Wind Farm located in the District Municipality of Namakwa.
• The 80MW Noupoort Wind Farm located in the Local Municipality of Umsobomvu in the Northern Cape.

The debt for the projects has been arranged and underwritten by Barclays and the Development Bank of Southern Africa. The consortium of Murray & Roberts and Conco has been appointed as construction contractor and Siemens Wind will supply and install the wind turbines. Simmons & Simmons and Bowman & Gilfillan acted as Lenders’ Legal Advisor. Fasken Martineau and Stoel Rives acted as Sponsor Legal Counsel.
The equity members of the consortium consist of:
· Mainstream Renewable Power.image

· Actis, through its Actis Energy 3 Fund, a leading energy investor in emerging markets.
• Thebe Investment Corporation; one of South Africa’s most established broad based BEE Investment management companies (advised by Bridge Capital).
• The IDEAS Managed Fund, managed by Old Mutual Investment Group, one of Africa’s largest independent investment managers.
• Futuregrowth Asset Management, a leading investor in developmental assets.
· Genesis Eco-Energy in partnership with Lereko Metier Sustainable Capital. Genesis Eco Energy is a pioneering South African renewable energy developer which has been active in South Africa since 2001. Lereko Metier Sustainable Capital is a resource efficiency private equity fund that has supported two of its investors DEG (The German Development Bank) and FMO (The Dutch Development Bank) in the investment across the Mainstream portfolio.

• Local Community members through established community trusts.

http://www.evwind.es/2015/02/12/mainstream-completes-financial-close-for-three-wind-power-farms-in-south-afric/50452 

 



Eólica y energías renovables en Argentina: proyecto eólico con 85 aerogeneradores

$
0
0
López, quien ayer acompañó al gobernador Martín Buzzi en el encuentro con el ministro de Planificación Federal de la Nación, Julio De Vido; sostuvo, en declaraciones radiales, que el parque eóico estará ubicado en la zona de El Escorial, contará con 85 aerogeneradores que en total aportarán 200 megavatios de energía eólica al sistema y su construcción demandará 435 millones de dólares. El Parque Eólico “El Angelito” será el más importante de Sudamérica.


Estará ubicado en la Meseta chubutense, en la zona de El Escorial. Su construcción, acordada entre el Gobierno Nacional y China, demandará una inversión de 435 millones de dólares. El mes próximo comenzarán las reuniones con las empresas locales que tengan a su cargo la logística, obras civiles y montaje de aerogeneradores.
Consideró el funcionario que “es una muy buena noticia para la industria metalmecánica, pero también para nuestra Meseta porque va a generar no sólo puestos de trabajo genuinos sino también una proyección, porque el tener este parque eólico va a permitir, con el tiempo, que podamos ir saliendo de la generación aislada”.
López remarcó que los acuerdos suscriptos entre Nación y China “establecen que toda la logística, las obras civiles, el montaje de las torres sea con empresas y mano de obra local”. Además señaló que en Chubut “hay ingeniería y capacidad empresarial disponible” para llevar adelante este proyecto.
El ministro recordó que “hoy en consumo de combustible estamos gastando más de 15 millones de pesos anuales, dinero que ahora vamos a poder ahorrar y hacer otras líneas en media y baja tensión, con lo cual esto también permite la posibilidad de tener emprendimientos productivos, de mejorar en los sistemas de captación de agua”.
Por último aclaró que estos proyectos “son totalmente sustentables” y destacó que la “virtud de los vientos que tenemos es que están dando unos índices de eficiencia muy altos, por eso posiciona a Chubut dentro del primer lugar de generación de energía limpia y sustentable”.





Chile instalará la mitad de la energía solar fotovoltaica de toda Latinoamérica en 2015

$
0
0
De acuerdo al informe de GTM Research, en la región de América Latina se instalaron 625 megavatios de energía solar fotovoltaica (FV) en 2014, lo que corresponde a un aumento del 370% en el crecimiento anual en comparación a 2013. Se espera que la cifra se triplique este año con 2,1 gigavatios de FV.

El estudio asegura que cerca de la mitad de esta energía será generada en el país, principalmente en el norte.
El informe señala que “con su fuerte mercado de servicios a gran escala,Chile lideró la región en instalaciones fotovoltaicas en 2014, lo que representa más de las tres cuartas partes del total de América Latina”. Además agregan que sólo “en el cuarto trimestre Chile instaló el doble de la cantidad del total anual de América Latina en el año 2013”.
Lo más relevante, según el estudio, es que Chile comenzó el 2013 con sólo 11 megavatios de capacidad solar instalada. La rapidez con la que ha avanzado el país lo ha posicionado cómo líder de la región, por sobre México y Brasil, en cuanto a crecimiento.
Si bien mirando las cifras anteriores estas son sumamente positivas, en el futuro serán mejores, ya que hay casi 20 gigavatios en diferentes iniciativas anunciadas y en construcción. La cantidad de proyectos en la región llega a 514 y el monto es cercano a los 26 mil millones de dólares, asegura el estudio.
Si bien tanto a Chile como a los demás países latinoamericanos les queda mucho por avanzar para entrar en el top 10, o para tener un alto porcentaje de capacidad solar total inyectada en la matriz energética, nadie puede desconocer que la tasa de crecimiento actual, la que llega a más del triple en un año, es de gran relevancia.


Iberdrola and BMW launch corporate electric car sharing service

$
0
0
Iberdrola and BMW have launched the first corporate electric car sharing service in Spain, based on the i3 model by the German manufacturer. This 100% electric vehicle will be used at the electric utility's centres in Madrid, Bilbao, Barcelona and Valencia.
Alphabet, the contract hire , fleet management and corporate mobility company belonging to the BMW group, will be in charge of providing the cars and of designing and implementing the solution for managing this service, which will initially run for four years, according to the recently signed agreement.
This car-sharing service will give almost 350 members of staff at Iberdrola access to environmentally-friendly cars when doing retail business in the four cities mentioned above. This will improve their travel efficiency, by saving on costs and reducing CO2 emissions into the atmosphere by up to 4.68 tonnes.
The result of the MoU signed by the two institutions last year to develop areas of common interest in the field of electric mobility, this initiative follows BMW's commitment to offer Iberdrola's Green Energy product to customers buying electric vehicles
The combination of Iberdrola's Green Energy and BMW's electric vehicles is the best comprehensive solution for a form of mobility that is 100% emissions free, as it guarantees that no emissions are generated when travelling in these vehicles or in producing the electricity used to run them.  This enables the German brand to close the sustainable loop started in the design and production of the i3 and i8 models.
In 2010, Iberdrola launched a business area for developing and marketing charging solutions for electric vehicles.  Since then, the company has taken part in several electric mobility projects in Spain and in Europe, as well as acting as a Charge Manager, according to the role created by standing legislation.
On the basis of this work, Iberdrola has developed its own proprietary technology and know-how in providing charging services. This experience has enabled the company to market the Iberdrola 'Recarga Verde' product, a comprehensive solution that meets the charging needs of electric vehicles in both the public and private sectors. In particular, the 'Recarga Verde' Smart and Basic products are an ideal proposal for households, business fleets and shops and service providers with publicly accessible car parks that wish to offer their customers charging services.
In this regard, Iberdrola has installed a total of 224 charging points for electric vehicles in recent years, of which 19 were set up at the BMW headquarters, the brand's dealerships and other corporate centres belonging to the manufacturer in Spain.
About the BMW i3
The BMW i3 is a 100% electric car that generates an output of 170 hp and 0g/km in CO2 emissions. Its manufacturing process is driven by sustainable, state-of-the-art methods at the Moses Lake plant. The vehicle frame is made from carbon-fibre-reinforced plastic (CFRP) and recycled materials are used in the finish.  This guarantees a low overall weight, which combined with its powerful engine and design entirely geared towards electric mobility means that the BMW i3 is capable of a range of up to 190 kilometres on a single charge and of accelerating from 0 to 100 km/h in just 7.2 seconds.  The peak torque is 250 Nm, which is on tap immediately.


 


Iberdrola y BMW lanzan el primer servicio de car sharing con vehículos eléctricos

$
0
0
Iberdrola y BMW han lanzado el primer servicio de car sharing eléctrico corporativo en España mediante el vehículo eléctrico i3 de la marca alemana, 100% eléctrico, que se utilizará en los centros de la compañía eléctrica en Madrid, Bilbao, Barcelona y Valencia.


La compañía de renting, gestión de flotas y movilidad corporativa Alphabet, perteneciente al grupo BMW, será la responsable de aportar los coches y de realizar e implantar la solución para la gestión del servicio que, en principio y según el convenio recién firmado, tendrá una duración de cuatro años.

Gracias a este servicio de coche compartido, casi 350 profesionales de IBERDROLA podrán disponer de vehículos respetuosos con el medio ambiente para llevar a cabo gestiones comerciales en las cuatro ciudades mencionadas, lo que supondrá un incremento en la eficiencia de sus desplazamientos, al ahorrar en costes y reducir las emisiones anuales de CO2 a la atmósfera hasta en 4,68 toneladas.

Esta iniciativa, fruto del acuerdo de intenciones que firmaron ambas entidades hace un año para el desarrollo de áreas de interés común en el campo de la movilidad eléctrica, se suma al compromiso de BMW de ofrecer el producto Energía Verde Iberdrola a los clientes que adquieran un vehículo eléctrico.

La combinación de la Energía Verde Iberdrola y los vehículos eléctricos de BMW constituye la mejor solución integral para una movilidad 100% libre de emisiones, al garantizar que éstas no se generan ni en los desplazamientos con este tipo de vehículos ni en la producción de la energía eléctrica que los alimenta. Asimismo, la marca alemana cierra de este modo el ciclo sostenible iniciado en el diseño y producción de los modelos i3 e i8.

IBERDROLA lanzó en 2010 un área de negocio para desarrollar y comercializar soluciones de recarga para vehículos eléctricos. Desde entonces, la compañía ha participado en múltiples proyectos de movilidad eléctrica en España y en Europa y ha llevado a cabo su actividad como Gestor de Cargas, según la figura creada por la legislación vigente.

Gracias a todos estos trabajos, IBERDROLA ha promovido su propia tecnología y conocimiento en la prestación de servicios de recarga y, fruto de esa experiencia, la empresa comercializa la Recarga Verde Iberdrola, una solución integral que da respuesta a las necesidades de recarga de los vehículos eléctricos tanto en el ámbito público como en el privado. En particular, los productos Recarga Verde Smart y Basic representan una propuesta óptima para hogares, flotas de empresa y aquellos comercios y servicios que cuentan con plazas de aparcamiento de acceso público y quieren ofrecer a sus clientes servicios de recarga.

En este sentido, IBERDROLA ha instalado durante los últimos años 224 puntos de recarga para vehículos eléctricos, de los que 19 han sido habilitados en la sede de BMW, concesionarios de la marca y otros centros corporativos del fabricante en España.

El BMW i3 es un coche 100% eléctrico que desarrolla 170 CV y emite 0g/km de CO2. Su proceso de fabricación está impulsado por métodos sostenibles y vanguardistas en la planta de Moses Lake. El chasis del vehículo es de PRFC (plástico reforzado con fibra de carbono) y usa materiales reciclados entre los acabados del vehículo. Esto garantiza un bajo peso de conjunto que, junto a la gran potencia y al diseño que parte desde cero pensando en la movilidad eléctrica, se traduce en que el BMW i3 sea capaz de recorrer hasta 190 kilómetros con una sola carga y acelerar de 0 a 100km/h en sólo 7,2 segundos. El par máximo es de 250 Nm y se entrega de forma constante desde el primer momento.





NordLink HVDC interconnector between Norway and Germany will use Nexans’ subsea power cables

$
0
0
First ever power interconnector between Norway and Germany will be Nexans’ largest subsea power cable contract to date in terms of length and value Contract value is approximately 0,5 Bn Euros.


The Norwegian and German power grids will be able to share green energy directly for the first time thanks to Nexans submarine HVDC (high voltage direct current) cables to be installed as part of the NordLink project. Nexans will design, manufacture and install two 525 kV cable subsystems, with a total length of more than 700 km, off the coast of Norway and Denmark. The project, Nexans’ largest of this type to date, is due for completion in 2019. The contract value is approximately 0.5 Bn Euros.
The 1400 MW NordLink VSC (Voltage Source converter) HVDC project, a collaboration between Statnett,  TenneT and the German promotional bank KfW, will connect the Norwegian and German electricity markets to exchange green energy. Surplus wind and solar power produced in Germany can be exported to Norway. Conversely, hydroelectric power from Norway can be exported to Germany. This will be an important contribution to the future development of climate-friendly energy.
Nexans will design, manufacture and install mass impregnated non-draining (MIND) HVDC cables at depths down to 450 metres off the coast of Norway and Denmark. The cables will be laid by Nexans’ own cable-laying vessel, C/S Nexans Skagerrak  and protected on the seabed by trenching with Nexans’ Capjet system.
The Nexans power cables will feature the same reliable and well proven design implemented for the successfully completed installations of the Skagerrak 1, 2, 3 projects, and more recently the Skagerrak 4 project for the 140 km subsea HVDC interconnector between Denmark and Norway.
Dirk Steinbrink, Nexans Senior Executive Vice President High Voltage & Underwater Cables, said, “The NordLink project will be Nexans’ largest subsea power cable contract to date in terms of length and value and we look forward to continuing our close working relationship with TennetT, KfW and Statnett on this important project. The key to this success is our state of the art subsea cable technology combined with the proven capability to handle complete turnkey projects from design through to installation. We are excited to be involved in the Nord.Link which is a further step towards a complete integration of the European power grid.”

http://www.evwind.es/2015/02/12/nordlink-hvdc-interconnector-between-norway-and-germany-will-use-nexans-subsea-power-cables/50460 

  

Wind energy in Philippines: new wind farm with Vestas wind turbines

$
0
0
The Philippines’ prime renewable sources of energy include geothermal energy, hydro, wind power, and solar energy.


Two new wind farms have become operational in the Philippines, supplying 303 megawatts of clean energy to the country’s energy portfolio.
The wind farms are located in Ilocos Norte and Panay region of the Philippines.
Last year, a $220-million, 81-megawatt wind farm was opened in Pagudpud, Ilocos Norte as a solution to the power crisis challenge faced by the country.
In another development, the Philippines power-producer Energy Development Corporation (EDC) has grid-connected the nation’s largest 150MW Burgos wind farm worth $450m.
Burgos uses 50 V90 3MW wind turbines from Vestas at Ilocos Norte province.
According to the Wind Energy Development Association of the Philippines, the highest wind energy output occurs during March of each year.
WWF’s Seize the Wind campaign aims to increase the Feed-in Tariff (FiT) allocation for wind energy from 200 MW to 500 MW.
Wind farms need only a year to go online, compared with fossil-fuel power plants which take up four years to complete construction.
In Philippines, around 70 percent of the electricity is generated from fossil fuels.
As the country does not have any considerable amount of fossil-fuel deposits, major portion of the fuel needed for the country is imported from other nations.
On the other hand, President Aquino has urged the country to invest in renewable energy to ensure adequate power supply that would not be harmful to the environment.
The country’s National Renewable Energy Program aims at adding 9,931 megawatts of renewable energy-based capacity by 2030.


 

China's installed wind power capacity hit record high in 2014

$
0
0
The wind power sector generated 134.9 billion kilowatt hours of electricity in China in 2013, making it the country's third-largest source of electricity, after thermal power and hydro power.

 China's newly installed wind power capacity jumped to a record high of 19.81 million kilowatts in 2014, according to an industry briefing by the National Energy Bureau (NEB) Thursday.
Wind power generated 153.4 billion kilowatt hours of on-grid electric power in 2014, contributing to 2.78 percent of the country's total generated electricity, said Shi Lishan, deputy director of the NEB's new and renewable energy department.
The year saw more wind power construction and development, with newly-approved wind power capacity reaching 36 million kilowatts, a year on year increase of 6 million, Shi said.
The average usage of wind power in 2014, however, slumped to 1,893 hours from 2,074 hours in the previous year, partly due to weak wind conditions throughout the year, Shi added.


 

Turkey’s wind energy capacity increases over 3,000 MW in 2014

$
0
0
Turkey’s wind power capacity increased to over 3,000 megawatts (MW) with the installation of new facilities totaling 804 MW in 2014, according to wind power body the Global Wind Energy Council (GWEC).


Turkey’s wind power capacity rose to 3,763 MW in 2014, according to the GWEC’s Global Report, which also showed the growth of the wind power industry around the world.

“After a slowdown in 2013, the global wind industry set a new record for annual installations in 2014. Globally, 51,477 MW of new wind-powered generating capacity was added in 2014,” said the report.


The European market grew marginally in 2014, with 12,820 MW of new capacity, just shy of 2012’s record, the statement said.

Germany’s 5,279 MW of new capacity smashed the old record and cemented the country’s position as the European market leader, with the U.K. a distant second at 1,736 MW. Sweden passed the 1,000 MW mark for the first time with 1,050 MW, and France was the last of four European markets surpassing 1 GW, with 1,042 MW installed last year.

China continued to drive global wind power growth, setting a new record in 2014 with 23,351 MW of new wind power, representing 45 percent of the global market.

The world-leading Asian market’s total installations amounted to 26,161 MW, with India’s 2,315 MW a distant second to China, although the report said the stage had been set for a new round of market growth in that country.
Overall, this year’s record-setting figure represented a 44 percent increase in the annual market, and was a solid sign of the recovery of the industry after a rough patch in the past few years, with a cumulative total from installations standing at 369,553 MW at the end of 2014, said the report. 


 

Plan for Australia's largest solar power (2,000 MW) approved

$
0
0
Australian local government authorities this week approved a plan to build the nation's biggest solar energy plant at a cost of more than 1 billion U.S. dollars.

The Toowoomba Regional Council approved the staged construction of a 5,000 hectare site at Bulli Creek in southwest Queensland and developer Solar Choice plans to start construction next year.
The solar power plant will have the capacity of producing 2,000 megawatts (MW), more power than any one coal-fired power station in Queensland.
Solar Choice managing director Angus Gemmell said the approval came after 18 months of planning.
"It's almost mind-boggling large, just the width of the project is eight kilometers," he told Australian Broadcasting Corporation.
"It's soaked in sunshine, there's great irradiance levels west of the Great Divide," he said.
Gemmell said the project has attracted strong overseas investor interest, and would be completed in stages over eight years.



Cener participa en Atlas de Energías Renovables

$
0
0
CENER participa en Atlas del potencial de las energías renovables de IRENA para la eólica, fotovoltaica, geotérmica y termosolar. Esta nueva versión, de acceso libre desde la web oficial de IRENA, supone una importante actualización de la información que existía hasta el momento. Actualmente es posible consultar mapas (los datos están en formato GIS) de recurso de energía solar, eólica, geotérmica, bioenergía y energía marítima.

Durante una reunión celebrada en Abu Dabi los días 17 y 18 de enero, IRENA Agencia Internacional de Energías Renovables), CENER (Centro Nacional de Energías Renovables-España), el centro aeroespacial(DLR-Alemania), MasdarInstitute (Emiratos Árabes Unidos), el Laboratorio Nacional de Energías Renovables (NREL-USA) y MINES ParísTech (Francia) anunciaron en la 5ª asamblea anual de IRENA el lanzamiento del Global Atlas 2.0.
Esta nueva versión, de acceso libre desde la web oficial de IRENA, supone una importante actualización de la información que existía hasta el momento. Actualmente es posible consultar mapas (los datos están en formato GIS) de recurso de energía solar, eólica, geotérmica, bioenergía y energía marítima. Incluye además nuevas funcionalidades y herramientas como:
  • Galería de mapas: búsqueda de mapas por palabra clave, localización o recurso energético.
  • Infopicker: Acceso a datos, herramientas y perfiles de país desde REsource (portal web de conocimiento de IRENA).
  • Búsqueda en catálogo: ampliación de la búsqueda de datos por nombre, localización, palabra clave o calidad del dato (ésta última en versión beta).
  • Visualizador universal: visualización de datos de recursos eólico y solar en un click. Posibilidad de descarga de datos.
  • Mayor interactuación de los usuarios, que tienen la posibilidad de enviar comentarios a IRENA.
  • Compartir mapas y valores entre la red de contactos de los usuarios.
En el caso de CENER su trabajo como socio tecnológico ha consistido en el desarrollo de varias tareas y aplicaciones de funcionalidad relacionadas con la plataforma tecnológica del Global Atlas, que tenían como objetivo principal unificar en una herramienta los diferentes tipos de datos relacionados con la energía, para poder visualizarlos y poder generar las correspondientes gráficas y estadísticas. CENER ha trabajado en el apartado de datos eólicos y ha publicado datos de frecuencia y velocidad de todo el continente africano y en breve lo hará de Latinoamérica.

Global Atlas es una iniciativa coordinada por IRENA, en la que colaboran representantes de 67 países que conforman un consorcio internacional de expertos y proveedores de datos en formatos GIS.
Para más información se puede consultar el sitio web: http://globalatlas.irena.org


 
 

Bolivia instala su segunda central de energía solar fotovoltaica

$
0
0
Bolivia empieza a desarrollar las energías renovables,  como la eólica, energía solar fotovoltaica y la geotérmica, siguiendo el ejemplo de otros países de América Latina.
La empresa alemana Deea Solutions GmbH ganó la adjudicación para el diseño de una central de energía solar que se instalará en la región boliviana de Oruro para generar 20 megavatios de electricidad, informó ayer el ministro de Hidrocarburos y Energía, Luis Alberto Sánchez. 
"Debemos anunciar a la población que se adjudicó a una empresa alemana para el estudio a diseño final de la planta solar para el departamento de Oruro, que tendrá una capacidad de 20 megavatios (MW), los cuales serán inyectados al Sistema Interconectado Nacional (SIN)", acotó Sánchez.
La firma hará el estudio en un periodo de seis meses, entre marzo y agosto de este año, con una inversión de 250.000 dólares, explicó Sánchez. 
"El estudio determinará la ubicación exacta de la planta solar. Se estima que se instalen los paneles solares en una superficie de 35 a 40 hectáreas y el costo para la construcción es de 45 millones de dólares, aproximadamente", señaló el ministro. Añadió que la planta tendrá una capacidad de generación de 20 megavatios que irán al Sistema Interconectado Nacional (SIN). Estudios referidos a niveles de radiación solar demuestran que el territorio boliviano, en especial el altiplano boliviano, presenta uno de los mayores índices de irradiación solar del mundo. La de Oruro será la segunda generadora de energía solar que tendrá Bolivia, pues desde septiembre pasado opera en la región norteña de Pando, en la frontera con Brasil y Perú, una planta instalada por la empresa española Isotron, del grupo Isastur. Sánchez resaltó que aquella planta genera cinco megavatios y por ahora "ha dado buenos resultados". 
El Ministerio de Hidrocarburos y Energía destacó que el impacto de la plantas solares en el medio ambiente es "mínimo", puesto que estas industrias no emiten ninguna sustancia tóxica, ni gases contaminantes del aire, agua o suelo. "La operación de un sistema fotovoltaico es barata y el sistema requiere de un bajo mantenimiento en comparación a otras plantas", agregó la institución. Bolivia está empeñada en cambiar su matriz energética, que en la actualidad se sustenta en la generación termoeléctrica en un 65 %. Las autoridades han señalado varias veces que el objetivo es que para el bicentenario de la fundación del país, el 70 % de la generación de energía sea hidroeléctrica o provenga de otras fuentes alternativas como la eólica y la solar, y que el 30 % restante sea termoeléctrica.
 
 

Capacidad instalada de energía eólica de China alcanza récord en 2014

$
0
0
La nueva capacidad instalada de energía eólica de China alcanzó un récord de 19,81 millones de kilovatios en 2014, según se indicó en una sesión informativa de la Administración Nacional de Energía (ANE) celebrada el jueves.

Los parques eólicos generaron 153.400 millones de kilovatios/hora de electricidad transmitida a través de la red eléctrica nacional en 2014, aportando el 2,78 por ciento de toda la electricidad generada en el país, dijo el subdirector del departamento de energías nuevas y renovables de la ANE, Shi Lishan.
China registró una mayor construcción y desarrollo de la energía eólica el año pasado, y su una capacidad instalada de energía eólica aprobada alcanzó 36 millones de kilovatios, seis millones más que el año anterior, concretó Shi.
Sin embargo, el uso promedio de energía eólica en 2014 bajó a 1.893 horas, frente a las 2.074 horas del año anterior, debido en parte a las débiles condiciones del viento durante el año, añadió Shi.
El sector de la energía eólica de China generó 134.900 millones de kilovatios/hora de electricidad en 2013, con lo que la convirtió en la tercera fuente de electricidad, después de la energía termoeléctrica y la energía hidroeléctrica.




Tesla apuesta por baterías para los hogares

$
0
0
California ve el almacenamiento de energía como una herramienta fundamental para mejorar la gestión de la red eléctrica, integrar una cantidad cada vez mayor de energía solar y eólica, y reducir las emisiones de gases de efecto invernadero.

Tesla Motors, mejor conocida por hacer el modelo totalmente eléctrico S Sedán, está utilizando su tecnología de baterías de iones de litio para posicionarse como uno de los favoritos en el mercado emergente de almacenamiento de energía que complementa y, en última instancia, podría poner en peligro a la red eléctrica tradicional.
Tesla-Solar-energy
"Vamos a desvelar la batería para el hogar Tesla, la batería de los consumidores que será utilizada en las casas o negocios de las personas bastante pronto", dijo ayer el presidente ejecutivo de la empresa, Elon Musk, durante una conferencia telefónica.
teslawind
La combinación de paneles solares con baterías grandes y eficientes podría permitir a algunos propietarios evitar la compra de electricidad a los servicios públicos. Morgan Stanley dijo el año pasado que el producto de almacenamiento de energía de Tesla podría ser "perjudicial" en Estados Unidos y Europa ya que los clientes buscan evitar las tarifas por servicios públicos yéndose "fuera de la red". Musk precisó que el lanzamiento del producto se produciría en el próximo mes o en dos meses.
tesla-model-s
"Tenemos el diseño hecho, y su producción debería empezar en unos seis meses más o menos", señaló Musk. Tesla ya ofrece unidades de almacenamiento de energía residenciales para un selecto grupo de clientes a través de la empresa de energía SolarCity.
La fábrica de Fremont, California, de Tesla está haciendo sistemas de almacenamiento estacionarios más grandes para las empresas y los clientes de los servicios públicos.
El fabricante de automóviles con sede en Palo Alto ha instalado una unidad de almacenamiento en su estación Tejon Ranch Supercharger en la Interestatal 5 al sur de California y tiene varias otras instalaciones comerciales en el campo.
Las acciones de Tesla cayeron en las primeras operaciones ayer luego que el fabricante de automóviles eléctricos no cumpliera los objetivos de entregas y reportara una inesperada pérdida trimestral.
Los títulos bajaron 4,6% el jueves cuando Tesla anunció una pérdida en el cuarto trimestre, excluyendo ciertos ítems, de 13 centavos por acción, en una carta a los inversionistas publicada en su sitio web.
Los analistas habían estimado una ganancia de 32 centavos por acción, en promedio, según datos compilados por Bloomberg.
Tesla entregó un récord de 9.834 vehículos, superando la estimación promedio de los analistas de casi 1.000 y su propia meta de 1.345 automóviles.
La compañía dijo que si bien había cumplido con el objetivo de producción para todo el año de 35.000 autos Modelo S, muchos no se terminaron hasta fines de año y no pudieron ser entregados a los clientes en 2014 debido a las vacaciones de Navidad y un duro invierno.



 
 

Eólica en Honduras: Lunes inauguran nuevo parque eólico con 25 aerogeneradores

$
0
0
La eólica San Marcos tiene un costo de 140 millones de dólares. Consta de 25 aerogeneradores, con una capacidad de dos megavatios cada uno. El proyecto eólico fue construido en un tiempo récord de 14 meses.

El segundo proyecto de energía eólica en Honduras será inaugurado el próximo lunes.
Se trata del parque eólico San Marcos de Colón, la que fue construida por la empresa Vientos de Electrotecnias S.A. (Vesa) del Grupo Terra de capital hondureño. 

La capacidad instalada es de 50 megavatios. El primer parque eólico en el país fue inaugurado en febrero de 2012, conocido como Cerro de Hula, con una capacidad inicial de 102 megavatios.
Posteriormente se le incorporaron 24 megas adicionales, para una capacidad total de 126 MW.
Las pruebas de operación comenzaron a realizarse desde noviembre del año pasado. La ENEE sumará 176 megavatios de energía eólica en el sistema interconectado.






Eólica en Montenegro: Fersa vende una filial titular de un parque eólico

$
0
0
Fersa ha suscrito un contrato para la venta del 99% del capital de su filial en Montenegro titular del proyecto Mozura, consistente en la construcción de un parque eólico de 46 megavatios (MW).

El parque eólico, que se encuentra pendiente de construcción, ha sido vendido a la sociedad Cifidex, una filial de Vestigo Capital, anunció la empresa en una nota remitida a la Comisión Nacional del Mercado de Valores (CNMV).
El precio de la compraventa asciende a 2,9 millones de euros y se abonará cuando se hayan cumplido las condiciones suspensivas y se consume la operación.
La venta no tendrá impacto en los resultados de Fersa y se inscribe en la ordenación de la cartera de proyectos de la empresa para evitar la dispersión de su negocio.




Viewing all 10308 articles
Browse latest View live